Posted: 06/11/2014
In this second article considering how to challenge awards under the Arbitration Act 1996 (the 1996 Act), we look at challenges to an award on the ground of serious irregularity (section 68). Historically, successful challenges under s68 have been rare. To quote the Report of the Departmental Advisory Committee which led to the 1996 Act, s68 “is really designed as a long-stop, only available in extreme cases where the tribunal has gone so wrong in its conduct of the arbitration that justice calls out for it to be corrected”.
Recent case law demonstrates that this principle still very much holds true in practice.
Section 68 allows a party to arbitral proceedings to apply to court challenging an award on the ground of serious irregularity affecting the tribunal, proceedings or award. “Serious irregularity” means an irregularity of one or more of the types listed in s68(2) which the court considers has caused or will cause substantial injustice to the applicant. An applicant therefore needs to demonstrate first, that a serious irregularity has occurred; secondly, that the irregularity falls within one of the categories set out in s68(2), and thirdly, that the irregularity has or will result in “substantial injustice”.
Section 68 is a mandatory provision that parties cannot contract out of. If an applicant successfully proves that there is a serious irregularity, the court may remit the award to the tribunal for reconsideration, set it aside or declare it to be of no effect (in whole or part).
One of the more popular (and in the court’s eyes, overused) categories of serious irregularity is “failure by the tribunal to comply with section 33 (general duty of tribunal)” (s68(2)(a)).
In La Société pour la Recherche, la Production, le Transport, la Transformation et la Commercialisation des Hydrocarbures SPA v Statoil Natural Gas LLC [2014] EWHC 875 (Comm), the claimant argued that the tribunal had acted in breach of its duty under s33(1)(a) to act “fairly and impartially as between the parties, giving each party a reasonable opportunity of putting his case and dealing with that of his opponent” by allegedly overlooking and mischaracterising certain pieces of evidence.
Flaux J was unimpressed with the claimant’s application, which in reality amounted to an attempt to challenge the tribunal’s findings of fact. He reiterated that “the focus of the enquiry under section 68 is due process, not the correctness of the tribunal’s decision” and concluded that there was no question of absence of due process in this case.
Flaux J stressed that it is entirely inappropriate to use s68 as a mechanism for challenging the tribunal’s findings of fact. Quoting from his recent judgment in the Primera Maritime case he repeated:
“It is clearly not appropriate to use an application under section 68 to challenge the findings of fact made by the tribunal. If it were otherwise every disappointed party could say it had been treated unfairly by pointing to some piece of evidence in its favour which was not referred to in the Reasons or not given the weight it feels it should have been. That is precisely the situation in which the Court should not intervene. Matters of fact and evaluation of the evidence are for the arbitrators.”
This decision shows the courts upholding the finality of arbitration awards: s68 is not to be used as a backdoor route to appeals of fact. Practitioners considering a s68(2)(a) application should weigh up carefully whether the potential applicant’s complaint truly concerns a breach of process or whether in reality it is a complaint regarding the tribunal’s findings of fact. If it centres on the tribunal’s findings of fact, the court may intervene, but will only do so if the tribunal has gone so exceptionally wrong that justice demands the award’s correction. Flaux J noted that such cases would be extreme and rare.
That said, this year has provided at least one example of a (partially) successful s68 challenge involving s33(1)(a) (and therefore s68(2)(a)).
In Brockton Capital LLP v Atlantic-Pacific Capital, Inc. [2014] EWHC 1459 (Comm) the defendant, in a post hearing memorial, claimed that a sub-section of the underlying contract was an unforceable penalty. The claimant reserved its position on these new arguments but did not object to them. The tribunal allowed the defendant's new submissions, but its award referred to the whole of the particular section of the contract as being a penalty, rather than just the sub-section.
Field J rejected the claimant’s first argument, finding that it had had an opportunity to object to the defendant’s new arguments. By reserving its position the claimant had failed to take that opportunity, and the tribunal was entitled to assume that the claimant had decided not to make submissions on the new argument. This meant that on that occasion, there was no breach of s33.
On the other hand, by referring to the whole section rather than just the sub-section, the tribunal had decided a further new submission introduced by the defendant (that a second subsection was also a penalty). The claimant had not had notice of this new submission and therefore had not been given the opportunity to address it. That amounted to a breach of s33, and that irregularity caused substantial injustice to the claimant. The application succeeded on this second point and the award was remitted back to the tribunal for reconsideration.
Field J observed that there is an important distinction between a party being given no opportunity to address a point, and a party failing to recognise or take the opportunity that exists.
The claimant also argued that the tribunal’s failure to refer to the evidence of one of the witnesses was a breach of its s33 duty. This argument did not find favour with the court, which concluded that “it will only be in the most exceptional case, if ever, that a failure to refer to a particular part of the evidence will constitute a serious irregularity within s68”.
In Interprods Limited v De La Rue International Limited [2014] EWHC 68 (Comm) the Commercial Court dismissed challenges brought under both s67 and s68.
The claimant identified three serious irregularities in the arbitrator’s conduct of the arbitration, which it claimed were in breach of s33 and s68(2)(a):
Dismissing the claimant’s application, Teare J found that the arbitrator’s decision to proceed with the conference call in the claimant’s absence was “robust but fair” given that the claimant had been invited but declined to participate. The allegations of bias were rejected. The arbitrator’s findings at the evidential hearing which the claimant also chose not to attend were also found to be fair.
It seems therefore that the spirit of Jackson extends to the arbitral process too, and the courts will support tribunals using robust but fair case management methods in order to progress the arbitration where a party is being uncooperative.
Disgruntled parties to an arbitration need to be very aware of the challenges they face in seeking to overturn an arbitral award on the ground of serious irregularity. The focus of any such challenge must be on the process and procedure used rather than the tribunal’s findings of fact. The parties must also have taken every opportunity available to them to put their case to the tribunal.
In the words of Field J in Brockton: “The threshold of the test of a serious irregularity giving rise to a substantial injustice is set deliberately high because the purpose of the 1996 Act was to reduce drastically the extent of intervention by the courts in the arbitral process. Thus relief under s68 will only be appropriate where the tribunal has gone so wrong in its conduct of the arbitration that justice calls out for it to be corrected.”
An applicant must prove one or more of the following kinds of irregularity (s68(2)):
|
Having proved the existence of such an irregularity, the applicant must convince the court that it has caused or will cause the applicant “substantial injustice”. There is no single test for deciding whether an irregularity has caused or will cause substantial injustice: it will be very fact specific. As a rule of thumb, the court will need to be satisfied that, but for the irregularity, the applicant would have dealt with the matter differently or the outcome would have been materially different (Chantiers de l’Atlantique SA v Gaztransport & Technigaz SAS [2011] EWHC 3383).
This article was published in New Law Journal in October 2014.