Posted: 16/12/2022
It is often assumed that utilities will be readily available to connect into, or easy to remove or divert on a new build development, and therefore there is very little importance placed on the installation and presence of service media during the planning stage. This presumption can be a costly mistake for property developers.
It is important to carry out enquiries of the relevant service providers – this includes gas, electricity, telecommunications, water, sewerage, drainage and even various rail operators. The developer will then be able to identify:
Inevitably, on a development site acquisition, it is vital for a developer’s solicitor to carry out a utilities search, which should reveal any apparatus belonging to utility companies within the boundary, and vicinity, of the property – accompanied with plans as standard.
In the case of Spire Property Development LLP v Withers LLP, the relevance of utility searches/enquiries relating to utilities was reviewed by the court. The facts of the case are as follows.
In 2012, two property developers purchased two adjacent properties in London for development. After completion, the developers discovered that three high-voltage electric cables owned by UK Power Networks (UKPN) ran beneath the properties. Unless removed, the cables would significantly limit the scope of the re-development.
The solicitors acting on behalf of the developers did not carry out a power-line search. The developers asked their solicitors: (1) why the existence of the cables had not shown up before completion; (2) to elaborate on UKPN's statutory rights of access; and (3) if there was some kind of legal documentation relating to the laying of the cables on both sites.
The answers to the relevant questions were: (1) the receivers selling the property had extremely limited information and no knowledge of the property; (2) wayleaves do not need to be registered at the Land Registry, and it is entirely possible that a wayleave was granted some time ago when the cable was originally laid and not known to the seller; and (3) there was nothing revealed in the pre-contract due diligence referring to the cable identified by the developer.
The solicitors told the developers that the Electricity Act 1989 permitted UKPN to install power lines under private land (ie, without such rights having to be formally documented/registered against the title to the property). However, they did not advise the developers of their rights and potential remedies against UKPN. Taking that to mean that no solution was available to them, the developers reduced the scope of the development.
The developers brought claims in negligence against the solicitors, arguing that they had been negligent in failing to conduct a power-line search and advise them as to their rights and remedies.
Since the developers were probing the solicitors about what should have been discovered in relation to the cables before completion, and not to the developers' potential rights and remedies against UKPN, this did not point to a broader construction because it simply asked for the solicitors' thoughts on the specific questions. By answering as they did, the solicitors had not assumed a duty to advise on the developers' potential rights and remedies against UKPN.
The key statements from the judgement are: